  • 1.  BAT (Business Acceptance Test)

    Posted 05/17/18 07:25 AM

    Hello ... I am looking for information about BAT (Business Acceptance Test) in TBM Community but I wasn't able to find any ... perhaps you can point me to the right direction, please. We are about to start that phase in Apptio project implementation for our company and I would like to know if we have any insight from Apptio's users/instructors.

    Regards

    Eduardo




    #CostingStandard(CT-Foundation)


  • 2.  Re: BAT (Business Acceptance Test)

    Posted 05/17/18 09:55 AM

    Hi Eduardo, 

     

    I don't believe we have a BAT specifically however we do have some Adoption resources.  I will tag you on them and I will move this post to a place that will have more visibility and try to get some customer experiences going for you too. 


    #CostingStandard(CT-Foundation)


  • 3.  Re: BAT (Business Acceptance Test)

    Posted 05/17/18 10:05 AM

    Very much appreciated

    Eduardo


    #CostingStandard(CT-Foundation)


  • 4.  Re: BAT (Business Acceptance Test)

    Posted 05/17/18 10:33 AM

    I"m in a lab assist now.  I will tag you and move this asap.


    #CostingStandard(CT-Foundation)


  • 5.  Re: BAT (Business Acceptance Test)

    Posted 05/18/18 02:40 PM

    Can you please elaborate a little bit more how Adoption resources would help ...


    #CostingStandard(CT-Foundation)


  • 6.  Re: BAT (Business Acceptance Test)
    Best Answer

    Posted 05/18/18 03:53 PM

    On initial roll-out...done three now...I reach a point in the delivery roadmap where specific stakeholders/partners/allies are brought into the mix to perform a "validation" of the numbers, designs, etc planned for production usage.

     

    For each milestone reached in the roadmap, another round of validation exercises are executed with relevant stakeholders/partners/etc and specific steps/outcomes listed out for those validation exercises.

     

    Beyond the roadmap delivery, recurring "operational" validation exercises are identified in such a way as to register those parties involved/accountable (think RACI), frequency, and escalation points. The collection of which acts as a barometer to determine if a push to production usage reaches sufficient approval level or needs to be delayed. I say "sufficient" because there are times certain data sets, reports, etc may not get a full approval/validation, but it's agreed that no response can be regarded as a non-specific approval whereas the period of time solicited for such acts more as an opportunity to object to a production push.


    #CostingStandard(CT-Foundation)


  • 7.  Re: BAT (Business Acceptance Test)

    Posted 05/18/18 04:15 PM

    Very interesting answer and helpful too, since I work for a bank and we have a defined BAT process that we plan to follow in parallel with Apptio implementation and your answer gives me a very interesting overview on how other companies apply the business acceptance tests.  


    #CostingStandard(CT-Foundation)


  • 8.  Re: BAT (Business Acceptance Test)

    Posted 05/29/18 06:10 PM

    Part of my experience comes from Bank of America. :-)


    #CostingStandard(CT-Foundation)