Cognos Analytics with Watson

 View Only

Data Set Refresh Time

  • 1.  Data Set Refresh Time

    Posted Fri June 17, 2022 10:49 AM
    Hi,
    I am using a couple of data sets behind some reports.  A database view is the source to those data sets.

    The data sets have scheduled to refresh every day in the morning.  The below fig 1 is the snap shot of the data sets run time part of a scheduled job.  It shows a data set takes time around 10 minutes and other one does 12 minutes.  Whereas fig 2 shows actual time taken to refresh each data set thru its properties.  They show max 4 minutes.  In this case, why does the schedule always takes around 12 minutes to complete?  Is there any other factor for the cause ?  Could anyone help me to understand?

    Please let me know if you have any questions.


    Fig. 1


    Fig. 2


    Thanks
    Regards,
    Karthik

    ------------------------------
    Karthikeyan Balasubramaniam
    ------------------------------