  • 1.  Scheduling tasks that need two resources

    Posted Mon March 22, 2021 10:14 AM
    Hello,

    I am looking at a scheduling problem where each task requires two resources simultaneously, such as a machine and an employee.

    The difficulty is that the resources have different availability calendars, and a task can only progress at times where both required resources are available.

    When scheduling for a single resource, I can use one interval variable per task and a stepwise intensity function to model resource unavailability. This idea does not seem to carry over to the two-resource case.

    What would be good ways to model this?

    Thanks,
    Joachim

    ------------------------------
    Joachim Schimpf
    ------------------------------

    #DecisionOptimization


  • 2.  RE: Scheduling tasks that need two resources

    Posted Mon March 22, 2021 11:34 AM
    Hi,

    One way could be to mix 2 stepwise functions to build a third one ?
    Other way, why not using 2 interval variables with 2 intensity functions and make those 2 intervals equal or at least link them ?

    regards

    ------------------------------
    [Alex] [Fleischer]
    [EMEA CPLEX Optimization Technical Sales]
    [IBM]
    ------------------------------