Originally posted by: SystemAdmin
Hi,
How can I model resource splitting, in a way that, part of a task could be assigned to one resource, and the rest of the same task could be assigned to an other resource. An example case could be, scheduling a long (multi day) duration task (longer than one worker's shift duration), and assigning one worker during morning shift and an other resource in the evening shift.
thanks a lot,
Mehmet.
#ConstraintProgramming-General#DecisionOptimization