Question about extending the End Date for AIG Projects

  • 1.  Question about extending the End Date for AIG Projects

    Posted 02/02/17 11:40 AM

    Apptio Support,

     

       I am currently trying to extend the following project end dates to December of 2017. I am receiving a “Permission Denied” error message. Do I need to work with an Apptio Admin to extend the end dates on our projects?

    Rich Larkin

    908-337-2468

     

    AIG Apptio Environments

    https://aig-dev.apptio.com/biit/

    https://aig-dev2.apptio.com/biit/

    https://aig-stg.apptio.com/biit/

    https://aig.apptio.com/biit/#

    https://aig2.apptio.com/biit/

     

    AIG Apptio Projects

    Project: TS Cost Transparency

    Project: BIO Cost Transparency

    Project: Science BIO CT Test

    Project: All IT Labor




    #CostingStandard(CT-Foundation)


  • 2.  Re: Question about extending the End Date for AIG Projects

    Posted 02/02/17 01:03 PM

    Richard,

     

    The time settings are controlled in your stage project where you load data.  If you go to Stage you should be able to extend the project time for the next fiscal year.  Then you would need to push the data project to the other environments to have the time extended through the project promotions tab.

     

    Steps for doing this would be:

    How To: Extend the date range of a project 

     

    Thanks,

    Ryan


    #CostingStandard(CT-Foundation)