Originally posted by: Haktan
As part of my thesis project, I was given a house building problem. There are 17 tasks in total and some tasks need to be completed before others. There are also 5 different worker types (builder, architect etc) and each task requires different types and amount of workers. I am complete beginner in CPLEX OPL and using the tutorials provided, I was able to minimise the time taken to complete the 17 tasks. I used dvar intervals and endBeforeStart() for this purpose. However, I have spent countless hours trying to add workers to my problem with no success. The examples only include workers with names; but in my problem I have different types of workers which the tasks require, and each type has a different number of workers available. How can I add workers to my problem and allocate them to each task in an optimal way? I'm really stuck any help would be amazing! (I've attached my current code to the txt file)
#CPLEXOptimizers#DecisionOptimization