  • 1.  CP4AIOps PoC Technical Planning Guide

    Posted Thu February 05, 2026 01:22 AM

    This document is purely focused on CP4AIOps PoC technical planning, all the project management parts (teams, timelines) are out of scope.

    1. Requirements

    For a PoC, the customer should release a full use case list, or a RFx document which can be used to extract all the use cases and get agreement on the use case list for the PoC with the customer.

    2. Data Collection

    2.1  Collect technology domains in scope

    Different customers in different industries will use different technology stacks. Telcos will be more focused on networking, and Banks will be more focused on servers and applications and possibly have systems running in cloud.

    Collect the customer industry category and technology domains like IT, Networking and cloud.

    2.2  Collect inbound integration sources and data volume

    2.2.1          The devices generate the data sets including alerts, metrics and logs

    2.2.2          Existing EMS list including names and versions, also the data types collected in each EMS including alerts, metrics, topology and logs

    2.2.3          Dedicated OOTB integration availability including connectors, observers and probes

    2.2.4          Other supported integration methods including webhook, file ingestion and Kafka

    2.2.5          Customized integration methods if no OOTB integration is available

    2.2.6          If possible, get data volume of each data type to determine the hardware sizing, in most of cases a production sizing should be sufficient for a PoC

    2.3  Collect outbound integration targets

    2.3.1          Ticketing 

    2.3.2          Runbook automation

    2.3.3          ChatOps

    3.  Solution Design

    3.1 Internet access: online or air gapped

    3.2 Deployment mode: OpenShift or Linux

    3.3 Hardware sizing: use production sizing by default, if the data volume exceeds production sizing processing capabilities, custom sizing will be calculated

    3.4 Storage provider: pick available storage provider and add storage hardware sizing into the solution

    Dependencies

    4.1 Infrastructure readiness including VMs, Subnets, DNS names and proxy

    4.2 Internet access: download the images online or for air gapped environment

    4.3 Firewall configuration: allow traffics between data sources and AIOps

    4.4 Device and EMS integration credentials: SNMP strings, URLs, Username/password and tokens

    4.5 Remote access: if remote VPN access is available 

    5. PoC Task Breakdown

    Create a PoC task list with details and ownership, status and timestamp

    6. Revised Use Case List and Success Criteria

    After the solution design and dependency checking, the use case list should be finalized by removing the use cases cannot be delivered in the PoC if the dependencies cannot be fulfilled.

    Based on the finalized use case list, discuss technical details with the customer, and get agreement on success criteria on each of the use case in scope. 

    7. PoC Delivery and Completion

    7.1 Deploy the solution with all integrations

    7.2 Show case all use cases match success criteria and record the test results

    7.3 Final presentation to wide audiences and collect feedback

    7.4 Submit PoC reports

    8. Appendix:

    A few templates can be used to start with.

    8.1  Data Collection template

    Technology

    Domains

    Source

    Devices

    Source

    EMS

    Data Types and volume

    OOTB Integrations

    Customization Required

    Alerts

    Topo

    Metrics

    Logs

    Connectors

    Observers

    Webhook

    File

    Probe

    Networking

    IT

    Cloud

    8.2  Dependencies and PoC Task Breakdown template

    Category

    Tasks

    Customer Owner

    IBM Owner

    Start Date

    Current

    Status

    Ready

    Date

    1.           Dependencies

    1.1 Infrastructure readiness

    1.2 Internet access

    1.3 Firewall permit

    1.4 Credentials

    1.5 Remote access

    2.           Installation

    3.           Inbound Integrations

    3.1 Alerts

    3.2 Topology

    3.3 Metrics

    3.4 Logs

    4.           Outbound Integrations

    4.1 Ticketing

    4.2 RBA

    4.3 ChatOps



    ------------------------------