WO.PCTASKCOMP: What is the intended use?

  • 1.  WO.PCTASKCOMP: What is the intended use?

    Posted 12 days ago

    MAM 7.6.1.2:

    In the WORKORDER table, I noticed there is a OOB persistent field called PCTASKCOMP:

    Toad:

    "Specifies the percent complete as calculated by tasks completed vs. planned."


    Question:

    What is the intended use for that field? Is there OOB logic that populates it?
     - I can't seem to find any information online or in the IBM ERD. Maybe it's a Maximo Scheduler field?



  • 2.  RE: WO.PCTASKCOMP: What is the intended use?

    Posted 11 days ago
    It is related to Scheduler (appears to have been added in the 7.6.5.0 version of Scheduler). I know it can be displayed in the Graphical Scheduling application but I'm not sure when that value gets updated exactly.

    ------------------------------
    Steven Shull
    ------------------------------



  • 3.  RE: WO.PCTASKCOMP: What is the intended use?

    Posted 11 days ago
    Yes, it is used for Scheduler.   In project management there are several ways to calculate or measure Percent Complete.   It can be by time spent, money spent, resources spent, number of jobs completed or by work accomplished.  PCTASKCOMP is one way.

    If you go to the Library tab on the Scheduler community:

    https://community.ibm.com/community/user/internetofthings/communities/community-home?CommunityKey=60718772-c63c-4d74-bdad-56d8beac4ba3

    and search for Percent you will find this document by Lori with a link to a Percent Complete video for possibly more than you want to know:

    https://community.ibm.com/community/user/iot/viewdocument/advanced-project-features?CommunityKey=60718772-c63c-4d74-bdad-56d8beac4ba3&tab=librarydocuments

    have a good weekend                               ....................dick

    ------------------------------
    Dick Chertow
    L2 Maximo Support