Olá Valter,
It's possible to skip V9, but you would still need to go V8 > V10 > V11 > V12.... the most critical part would be for application DBAs to check every incompatibility on all those versions (including V9) and possible fallback scenarios. Concerning the code, I would contact IBM support to see what are the options. If your customer have contract with GSD, is still possible to request older versions though.
There was a recent presentation from IBM lab that many customers are going from V11 > V12 > V13 where you wouldn't need to wait on each phase (CM/NFM or Function Levels). As all those phases are pretty stable for previous versions.
So, considering you are on DB2 V8 NFM, you would plan something on those lines:
- V8 NFM > V10 CM
- V10 CM > V10NFM > V11 CM
- V11 CM >V11 NFM > V12 FL100.
- Think about testing and possible fallback, because there are phases that you cannot fallback to previous version anymore.
- Application compatibilities, customer needs to make sure their applications continues to behave as expected and that they might need some modifications
- Also consider compatibilities with z/OS versions and other products/tools that connects to DB2 on each phase, you may need to also upgrade those (possibly more than once) to keep up with the Db2 version
Boa sorte :)
Ellen França
------------------------------
Ellen França
------------------------------
Original Message:
Sent: Fri June 13, 2025 04:00 PM
From: Valter Da Cruz
Subject: Upgrade IBM DB2 V8 to IBM Db2 V12 running under z/OS 2.4 on Z14
Estamos tentando fazer uma migração de de um DB2 v8 para um Db2 V12. Alguém conhece o step-by-step?
------------------------------
Valter Da Cruz
------------------------------