Task considerations/gotchas?

  • 1.  Task considerations/gotchas?

    Posted 10/14/20 01:43 AM
    Edited by System Admin 03/22/23 11:47 AM
    My organization has recently started using tasks in Maximo and we've been finding there have been some "gotchas" that we hadn't fully considered.

    Examples:

    1. WO cost summary reports should include tasks if the tasks have actuals.
    2. Tasks should be excluded from WO map layers in Desktop/Spatial and Anywhere.
    3. Task WONUMs could end up being a headache. Example: one of our external systems can only handle WONUMS with 7 digits. Utilizing tasks will mean we'll have a lot more WOs to contend with which could result in integration challenges

    Question:
    Are there any other gotchas or trade-offs that should be considered when using tasks in Maximo?

    Thanks.