Hi LLunuthara
for Assignment Manager, Graphical Work Week and Graphical Resource View applications the work hours in calendar shift will be applied. If you change your work hours on the shift to 7 hours that will solve the issues. The other scheduler apps will use the shift end time minus start time, breaks and shift work hours are ignored.
------------------------------
Lori Pilgrim
Maximo Design/Architect IBM
------------------------------