    Hello,

    I currently have assets that require Preventive Maintenance at different intervals, i.e (3 weekly,3mthly,6mthly and so on)

    What i can currently do is create a PM with sequenced Job Plans for the respective WO to be generated when it is due. For example,

    1st occurence - 3 weekly

    2nd - 3 weekly

    3rd - 3 weekly

    4th - 3 monthly

    But i need 2 work orders to be generated when different Job Plans coincide. for example when i am doing the 3 monthly, i need to do the 3 weekly as well. is there any way i can get 2 orders auto generated under a single PM when the job is due?

    For example, 1 work order for the 3 monthly and 1 work order for the 3 weekly.






    #Maximo
    #SupportMigration
    #Support
    #AssetandFacilitiesManagement


  • 2.  RE: Multiple Work Order Generation from Single PM

    Posted Mon July 20, 2020 08:55 PM

    Hi,

    I work in Maximo support. We talked about this one and decided you will need 2 PMs fi you want to make 2 work orders, one for the 3 monthly and one for the 3 weekly.

    Maybe you can make a combined or maybe a nested Job Plan to do the 3 monthly and the 3 weekly together when the 3 monthly should be generated. Then you could use one PM and when its the 3 monthly's turn to be generated it would use that combined Job Plan.

    regards ..............dick







    #AssetandFacilitiesManagement
    #SupportMigration
    #Maximo
    #Support


  • 3.  RE: Multiple Work Order Generation from Single PM

    Posted Tue July 21, 2020 05:45 AM

    Hi,


    thank you for the response. appreciate it