Hi Iswarya,
The PLUSCPMEXTDATE checkbox usually becomes unchecked when the PM schedule returns to normal - meaning the extended due date has been used, and Maximo recalculates the next due date based on the original frequency (like days or meter readings). This often happens after a work order is generated from the PM and the system resets the schedule.
It's also good to check if any custom automation scripts or configurations are affecting this behavior in your environment.
Hope this helps!
------------------------------
Arthur G
IS Engineer
------------------------------
Original Message:
Sent: Fri June 20, 2025 04:17 AM
From: Iswarya S
Subject: Maximo: Unchecking of Due Date Extended
Hi All,
In Maximo, under the Assets application, when does the PLUSCPMEXTDATE (Due Date Extended) checkbox become unchecked? In what scenarios does this checkbox get automatically cleared?
Thank in Advance
Regards,
Iswarya
------------------------------
Iswarya S
------------------------------