Purchase price = If you purchase the item marked as rotated, when you serialise it i.e. create the asset, the purchase price is captured.
Replacement cost = manually added
Total cost and YTD cost need to run the Maintenance Cost Rollup report or set the new correct System Property in MAS Manage
Budgeted = manually added
Inventory = whenever you raise a work order or PO and the CHARGESTORE is marked as Y, it will be accumulated here.
Current value = current depreciated value requires a depreciation schedule
Expected life = manually added
Estimated EOL = Installed date + Expected life
------------------------------
===============================