Hello Prashant,
I'm working with ACM and BDI (functional side), for railway train maintenance, for 2 years and I agree with you and Craig: some things are a magic in it !
We are testing a lot and have alway suprises (good or bad...)
The main difficulty when you start with ACM is to switch your mind about Asset Structure management, PM management, Meter management, condition based maintenance.
BDI is very powerfull and automates the creation and update of many data that you used to manage manually.
And if you use Maximo for Complexe Asset (former Maximo for Aviation), you will have some differencies in the ACM management...
I'll be happy to share what I know about and learn from other Maximo Experts all that I don't know until now ! :)
Kevin DUPONT - Malink (FR)
#IBMChampion
------------------------------
KEVIN DUPONT
Associate
MALINK
PARIS
+33681071128
------------------------------