The task may be a preparation activity that evaluates what is needed for the work order, the likely materials and safety measures needed, etc. The work order approval is a financial approval of the plans, this is why the planned estimates are saved at approval.
In the same way you may have tasks that are at WAPPR after the work order has reached COMP. In fact, you may create the task in the Actuals tab at COMP status. A good example is to update documentation.
Maximo is used in many industries/sectors and what may seem strange in one, may be quite normal in another, or what would be strange for one work type may be normal for another. Maximo, therefore, needs to be flexible and may not have those hard validations that sometimes you might expect. And, it cannot have all the business rules for validations for all industries/sectors - think how complex it would then become !
------------------------------
Andrew Jeffery
------------------------------
Original Message:
Sent: Mon October 25, 2021 03:43 PM
From: User1971
Subject: It's possible to change a task to INPRG while the WO is still WAPPR
MAM 7.6.1.2:
I noticed that it's possible to change a task's status to INPRG while the WO is still WAPPR.

That seems unintuitive to me. I would have thought that a WO would need to be INPRG in order for work to commence on tasks.
What would be the reason/use case behind that design decision?
Thanks.
#Maximo
#AssetandFacilitiesManagement