Hi Tim, thanks for the Maximo Secrets plug. My guess would be that the Dynamic Job Plans was solely focused on work orders. The functionality has been developed for years, you could download it from a Tivoli site ISM library. PM Forecast Costs came from same functionality in Maximo Scheduler - Graphical Scheduler. The PM Forecast costs may have been developed after the original Dynamic Job Plans, therefore I think it is an omission and a worthy candidate for an RFE. You should raise a case with IBM Support first, but I think the reply will end up as “not as designed” and then they will ask for you to raise the RFE. It is a great business scenario, I will vote for the RFE. Regards Andrew
Sent from my iPad