Hello,
Is it possible change user iteration rate while test execution in progress using rational performance tester.
Thankyou
Pathi
For a standalone test no
If test is in a schedule no, but if in a schedule if click on the "Running" pulldown menu we can change
For a Rate schedule, the same pulldown has an additional Change Rate... option, so the answer is yes, if you use a Rate schedule, introduced in 9.2.1 ? maybe 9.5