Hi,
I have the below scenario. Please help me with a solution in Maximo.
1. There is a Job Plan with 30 hours duration
2. Job Plan is associated to PM record which is due tomorrow (3/19/21)
3. PM record is set with Interruptible=1 and Crew Workgroup=XYZ
3. As per OOB: WO generated will have Target Start Date: 3/19/21 10:00 AM and Target Finish date: 3/20/21 4:00 PM though the PM is set for Interruptible=1
4. Expected outcome: Crew Workgroup can be associated with a calendar/ shift of 9 hrs each day
5. WO shall be generated with Target Start Date: 3/19/21 10:00 AM and Target Finish Date: 3/24/21 11:00 AM (considering shift starts at 8 AM and of duration 9 hrs and weekly holidays on Saturdays/ Sundays
Is there a feasible configurable solution in Maximo PM and WO for this above scenario?
Please suggest.
------------------------------
Venkataseshan Venkatasubramanian
------------------------------
#Maximo#AssetandFacilitiesManagement