Andrew, many thanks for the reply. I had come across your guides in my researching and I think GWW may be useful for some applications where we currently utilise Assignment Manager.
At the moment I am trying to explore use of Graphical Scheduling / Graphical Assignment as I think those are the apps that are aligned with Optimiser which we will need for some use cases.
I guess my original post was to try to get any useful experiences in use of scheduler in the day to day use with volumes of especially PM works.
Thanks again
Andrew
------------------------------
Andrew Blyth
------------------------------
Original Message:
Sent: Thu November 21, 2024 03:18 AM
From: Andrew Jeffery
Subject: Maximo Scheduler - real world use
Hi Andrew,
I did a deep dive on Graphical Work Week, you can find all the articles here https://maximosecrets.com/deep-dives/graphical-work-week/
The article on Assignments has a section towards the bottom called - Assign Multiple Assignments in one action.
Regards - Andrew
------------------------------
Andrew Jeffery
Maximo SME
ZNAPZ b.v
Barnstaple
+44 (0)777 1847873
Original Message:
Sent: Wed November 20, 2024 04:11 AM
From: Andrew Blyth
Subject: Maximo Scheduler - real world use
Hello
We are continuing our exploration of features in Scheduler. We will also be looking at automatic scheduling / assignment via Optimiser but that will be for a separate set of questions I imagine.
Our use cases will be around the scheduling and assigning of thousands of PM works a month.
I have reviewed the available training materials and videos (e.g. by Lacy) but lots of these seem to be from 2020 and I believe there have been enhancements to the graphical applications since then and the materials seem to be working on limited data sets and assigning a task at a time.
I can understand how the applications can be utilised to assign single assignments at a time - but not seeing how you can actually use the application when you have say 100's of unassigned works in a week and need to bulk assign them.
Are any of you using Graphical Assignment (would prefer this to Work Week as this I believe is more aligned to Optimiser) with these kind of volumes - how do you make it work for you. Are there more case studies / videos etc to illustrate this usage.
Thanks as ever for any help.
Andrew
------------------------------
Andrew Blyth
------------------------------