IBM FlashSystem

 View Only
  • 1.  Create backup on IBM Service Copy Manager with FS5300 Hyperswap

    Posted Thu January 09, 2025 04:53 AM

    Hello everyone, I am deploying Hyperswap with 2 FS5300 and IBM Copy Service Manager but when adding Snapshot Policies, I get an error as shown in the picture. I hope everyone can help me. Thank you very much.



    ------------------------------
    Tan Nguyen
    ------------------------------


  • 2.  RE: Create backup on IBM Service Copy Manager with FS5300 Hyperswap

    Posted Fri January 10, 2025 08:19 AM

    Hello Tan,

    you might want to look up the highlighted error id CMMVC8846E in IBM Docs.

    This article describes what to look at:

    CMMVC8846E The command failed because volume groups do not support both Safeguarded and snapshot policies

    That said, check for any existing policies and decide to go with either snapshot or safeguarded policies.



    ------------------------------
    Best regards, 

    Christian Schroeder
    IBM Storage Virtualize Support with Passion
    ------------------------------



  • 3.  RE: Create backup on IBM Service Copy Manager with FS5300 Hyperswap

    Posted Fri January 10, 2025 08:25 AM

    thank you for your interest in this article, sorry I was a little confused about the Snapshot Policy and Safeguarded Policy. what I'm stuck with here is that when executing Safeguarded Policy, the IBM Copy Service Manager Server lost connection and Volume backup could not work. I don't know why, hope you can help.



    ------------------------------
    Tan Nguyen
    ------------------------------



  • 4.  RE: Create backup on IBM Service Copy Manager with FS5300 Hyperswap

    Posted Fri January 10, 2025 09:37 AM

    There are two types of Safeguarded backup solutions on FlashSystem. 

    SGC 1.0 which is based on FlashCopy technology and requires a policy specified on the FlashSystem system which CSM discovers and automatically creates a CSM SGC session for...

    SGC 2.0 which is based on Snapshot technology.  The only policy on the FlashSystem is for the internal scheduler.  To manage Snapshots from CSM, a Snapshot session will need to be manually created with one or more scheduled tasks in CSM. 

    Are you referring to SGC 1.0 or 2.0?   The first post screen shot showed that you tried to do Snapshot when the volumes still had SGC 1.0 backups...which isn't allowed.  But think you understand that now. 

    The CSM screen shot seems to indicate to me that CSM is not up and running or did not startup correctly.  We won't be able to tell why from the screenshot.  Try restarting the CSM server....and if the problem persists you'll likely need to open a case.



    ------------------------------
    Randy Blea
    IBM
    (512) 286-5376
    ------------------------------



  • 5.  RE: Create backup on IBM Service Copy Manager with FS5300 Hyperswap

    Posted Fri January 10, 2025 12:05 PM

    Thank you, I think I am using SCG 1.0 to deploy on CSM. I am trying to do it to Backup a 40TB volume configured in Hyperswap mode on FS5300. But every time the backup schedule is executed, the CSM server automatically connects and the backup program does not work as I want. I hope you can help me to realize my mistake in the installation process. Here are some images of my deployment.

    • Server CSM.


    ------------------------------
    Tan Nguyen
    ------------------------------



  • 6.  RE: Create backup on IBM Service Copy Manager with FS5300 Hyperswap

    Posted Fri January 10, 2025 12:33 PM

    Not seeing anything in the screen shots that would be wrong....but not seeing any errors either.  In CSM open the Console and see if there are any error messages.  Also look at the Scheduled Tasks panel and validate that there is a scheduled task for that session and that it is enabled with the correct time. 



    ------------------------------
    Randy Blea
    IBM
    (512) 286-5376
    ------------------------------



  • 7.  RE: Create backup on IBM Service Copy Manager with FS5300 Hyperswap

    Posted Fri January 10, 2025 08:16 PM
    Edited by Tan Nguyen Fri January 10, 2025 08:18 PM

    Thank you, I have set the correct Safequard policy according to the schedule and it has been run. But when the Policy starts to be executed, the CSM Server automatically cannot connect. Let me ask if Volume Hyperswap when deployed with the CSM Server needs to go through the stage before executing the policy. Hope you can answer.

    Server CSM



    ------------------------------
    Tan Nguyen
    ------------------------------



  • 8.  RE: Create backup on IBM Service Copy Manager with FS5300 Hyperswap

    Posted Sat January 11, 2025 11:21 AM


    Hi, sir
    after I created the task to run every minute
    when it was time to execute the task, I lost access to CSM (https://localhost:9559/CSM)
    I could only access it again after restarting the 2 services IBM Copy Services Manager Authentication Service and IBM Copy Services Manager Server. During the time I lost connection, on the CSM server, I used the command to check the active ports (netstat -a) and did not find port 9559 open)

    After restarting the above 2 services, I could access CSM again, and had a state backup.
    I tried to restore a backup but it did not work, after restarting, when it was time to run the next backup schedule, CSM was disconnected again, forming a loop, restarting the services and having another backup error.

    - The first image is when the safequard policy had not been added

    • this is the image of safequard executed

    • I restart service.



    ------------------------------
    Tan Nguyen
    ------------------------------