  • 1.  Non-default craft in resource availability on GS

    Posted Thu January 27, 2022 10:44 PM
    Does GS (in 7.6.8) allow for factoring in non-default crafts into the resource availability for a shift?

    From the screenshot below, there are 20 hours in red for craft CIVIL; however all labor resources at this organization with craft ELECTRIC and MECHANIC could do CIVIL work as well, and CIVIL has been marked as their non-default craft. However, GS doesn't seem to take note of that?





    ------------------------------
    KKunnuthara
    ------------------------------



    #Maximo
    #MaximoScheduler
    #AssetandFacilitiesManagement


  • 2.  RE: Non-default craft in resource availability on GS

    Posted Fri January 28, 2022 01:46 PM
    Hello KKunnuthara

    Graphical Scheduling does not work with multiple crafts, only the default craft.  We have had heard this request before, however the degree of difficulty to ensure that we do not over book has prevented us to offering a solution for this.  At assignment time in Graphical Assignment and Graphical Work Week multiple crafts can be assigned to of course.

    ------------------------------
    Lori Pilgrim
    Maximo Design/Architect IBM
    ------------------------------



  • 3.  RE: Non-default craft in resource availability on GS

    Posted Sun January 30, 2022 06:55 PM
    Hi Lori,

    Thanks for that.


    Regards,

    ------------------------------
    KKunnuthara
    ------------------------------