Has anyone encountered any issue with upgrading from 9.0.7.2 to 10.0.4? We upgrade our Production ISAM over the weekend. All standard junctions connected fine to backend server, but our one virtual junction is a problem. It usually comes back as running but appears not to be HTTP server. I attempted to delete junction before upgrade and recreate it after but same issue. Below is some of the errors we are receiving on that WebSEAL instance.
DPWAD0432E Failed to execute the server task 'cluster last-modified' on dph-webseald-ccf084samp1.illinois.gov: HPDBA0219E An error occurred reading data from an SSL connection.DPWAD0438E Failed to synchronize with the cluster masterDPWAD0405E Failed to synchronize the WebSEAL server.Unable to delete this virtual junction icare from the proxy on either ISAM appliance in the cluster.System ErrorDPWWM2071E Could not delete Virtual Host JunctionDPWWA1225E Could not delete entry from junction database------------------------------
Patrick Davis
------------------------------