IBM webMethods Hybrid Integration

IBM webMethods Hybrid Integration

Join this online group to communicate across IBM product users and experts by sharing advice and best practices with peers and staying up to date regarding product enhancements.


#TechXchangePresenter
 View Only
  • 1.  Service monitoring in MWS - shows Activity instead of completed

    Posted Fri March 06, 2009 11:56 AM

    Hi Everyone,

    Need your help to resolve this issue.

    I have enabled audit logging for my flow service. But in MWS [Integration–> services], it is showing “Activity” sometime, and other time showing as “Completed”

    Environment: 7.1.2

    Please advise how to resolve this issue.

    Thanks in advance.!


    #webMethods
    #Integration-Server-and-ESB
    #Flow-and-Java-services


  • 2.  RE: Service monitoring in MWS - shows Activity instead of completed

    Posted Wed March 11, 2009 12:57 AM

    Whenever the status is “Activity”, the service might be running,and when the status is “completed”, the service is ran or process is complete.

    When the status is “Activity” log into IS Admin console and go to “Service Usage” and check the box “Show running services on top”. Your service should be listed as running, when the status is “Activity”


    #Integration-Server-and-ESB
    #webMethods
    #Flow-and-Java-services


  • 3.  RE: Service monitoring in MWS - shows Activity instead of completed

    Posted Mon March 16, 2009 10:26 AM

    The service execution already completed. If i open the service instance details, it is showing inside completed state. But main page it is showing as “Activity”


    #Flow-and-Java-services
    #webMethods
    #Integration-Server-and-ESB


  • 4.  RE: Service monitoring in MWS - shows Activity instead of completed

    Posted Tue November 20, 2012 03:11 PM

    Hi,

    Picking up this old thread. We have the exact same issue with incorrect status “Activity” on the main search page. Detailed page however shows correct status “Completed” (or “Failed”). Did you manage to resolve the problem?

    Kind regards,
    Daniel


    #Flow-and-Java-services
    #webMethods
    #Integration-Server-and-ESB


  • 5.  RE: Service monitoring in MWS - shows Activity instead of completed

    Posted Mon August 03, 2015 12:55 PM

    I see all the child services have “activity” status and the parent has completed/failed.

    Is n’t that normal?


    #Flow-and-Java-services
    #webMethods
    #Integration-Server-and-ESB