We are upgrading from RHEL7 to RHEL8 on ESXi VMs for our ILMT instance. The 20 x BES Relays have already been upgraded to RHEL8 and all working on our BF ILMT version (BF 10.0.7.52 and ILMT 9.8.28.0)
1 x Application server
1 x Database (DB2 11.5) server
They will be cloned for contingency....
The new RHEL8 servers will be 'given back' with same IP address and same hostname, but nothing migrated other than user accounts and groups.
DB2 will need installing on the Database server.
Application server will be not have any BF/ILMT installation.
QUESTION: Will the Backup and Restore procedures work here, which seem quite logical?
https://help.hcltechsw.com/bigfix/9.5/platform/Platform/Installation/c_backup_procedure_linux.html
https://help.hcltechsw.com/bigfix/9.5/platform/Platform/Installation/c_recovery_procedure_linux.html
...Or is there an alternate/better method?
Thanks in advance!