Hi Jonathan,
Yes you're correct. I tried the same and it seems the playbook can continue without the wait point 2. Thanks for the input. It was really helpful.
------------------------------
Dushan Dissanayake Information Security Engineer
------------------------------
Original Message:
Sent: Mon April 03, 2023 03:55 AM
From: Jonathan BULACH
Subject: IBM SOAR PLaybook Issue
Hi Dushan,
I didn't try it but I think the Wait point 2 is useless. You point waits for both branches to continue which will never happen because you have a condition before who runs only one of the two paths.
You should remove the Wait Point 2 and link the paths directly to the following task.
Hope I helped.
------------------------------
Jonathan BULACH
------------------------------
Original Message:
Sent: Fri March 31, 2023 07:17 AM
From: Dushan Dissanayake
Subject: IBM SOAR PLaybook Issue
Hi Priya,
Thank you for the response.
Please refer to the screenshot below which was taken from the playbook I've mentioned. The playbook only runs till the Wait Point 2 and shows the 100% completion of the tasks.
------------------------------
Dushan Dissanayake Information Security Engineer
Original Message:
Sent: Thu March 30, 2023 03:26 PM
From: Priya Sapra
Subject: IBM SOAR PLaybook Issue
Hi Dushan,
Can you share some information on what is happening before and what is meant to happen after the wait point? Additionally, if there is an error message that comes up, please share that as well.
------------------------------
Priya Sapra