Hi Everyone,
I am trying to setup graphical scheduler where All work orders are planned with no task , duration and craft with duration. I have seen same behaviour for PM work orders with tasks as well.
These work orders are displaying correct resource availability for the start dates and when we drag the work orders into different days as well.
But when we change work order duration i.e. decrease or increase work order duration , scheduler does not reflect the same in Resource availability.
- Screenshot with planned work of 7:20 showing the blue utilised hours in the resource availability:

2. In this screenshot the last work order duration is increased by 1.5 hours but the resource availability does not change.

My first guess is it is working as design and work order duration change will not change the craft duration.
Please let me know if I am missing something here and we can update the resource availability from changing work order duration in scheduler.
TIA
------------------------------
Biplab Choudhury