Resource Availability not updating when updating task duration in graphical scheduler

  • 1.  Resource Availability not updating when updating task duration in graphical scheduler

    Posted 6 days ago

    Hi Everyone,

    I am trying to setup graphical scheduler  where All work orders are planned with no task , duration and craft with duration. I have seen same behaviour for PM work orders with tasks as well.

    These work orders are displaying correct resource availability for the start dates and when we drag the work orders into different days as well.

    But when we change work order duration i.e. decrease or increase work order duration , scheduler does not reflect the same in Resource availability.

    1. Screenshot with planned work of 7:20 showing the blue utilised hours in the resource availability:

    2. In this screenshot the last work order duration is increased by 1.5 hours but the resource availability does not change.

    My first guess is it is working as design and work order duration change will not change the craft duration.

    Please let me know if I am missing something here and we can update the resource availability from changing work order duration in scheduler.

    TIA



    ------------------------------
    Biplab Choudhury
    IBM Champion 2022
    Solutions Consultant
    Valueztech Pty Ltd
    Melbourne VIC
    ------------------------------


  • 2.  RE: Resource Availability not updating when updating task duration in graphical scheduler

    Posted 2 days ago

    Hi Biplab,

    Confirm that duration has no effect on resource availability. Work Order plan craft/crew type is the source of resource demand for scheduler. Duration impacts the top section AKA the "Gantt". 



    ------------------------------
    Steve Norris
    ------------------------------