Maximo Scheduler Resource Loading is not updated when Work Order duration is updated in the Activity view

  • 1.  Maximo Scheduler Resource Loading is not updated when Work Order duration is updated in the Activity view

    Posted 6 days ago

    Hi Team,

    I have a graphical schedule with 10 work orders for 20th of feb and the total planned hours for the 10 work orders is 14 hours.

    All the 10 work orders are planned with no task, planned craft with duration and Work Order duration is planned.

    If I change one of the work order's duration i.e. previously the work order was planned for 2 hours but during scheduling the work I realised the work order will take additional 2 hours. If I change the work order duration from 2 hours to 4 hours , then graphical schedule didnt not update the labor loading and decrease the available by 2 hours.

    It is same behaviour for PM with tasks.

    My first assumption is that it is working as design and the planned craft duration needs to be changes then it will not work.

    Please let me know your thoughts on this.



    ------------------------------