Graphical Scheduling - Compliance defined 

Tue March 17, 2020 05:09 PM


Definitions

Scheduler has the ability to calculate and track two key time-phased work performance metrics:

  • Labor Hour Compliance Factor
    • The ratio of actual hours posted to planned work in the compliance period to the total number of planned hours at the start of the compliance period.
  • Work Order Compliance Factor
    • The ratio of planned work orders completed in the compliance period to the total number of planned work orders at the start of the compliance period.
Components
  • Scheduler Compliance tab
  • Header information about the period’s start and end
  • Manual actions to process a start and finish
  • Table of historical compliance periods
  • Line chart of the 2 data trend lines over the periods
Compliance Tab

Components
  • Scheduler Dashboard tab
    • Pie charts of the two main metrics for a selected period
      • Labor Hour Compliance
        • “Unplanned Hours” is (1 – (labor hour compliance)) as a percentage
      • Work Order Compliance
    • Stack chart of Schedule Compliance record counts
      • Plan Work Records
      • Break-in Work Records
      • Break-out Work Records
Dashboard Tab
Calculations
  • “Planning Set” – APPR work orders in the period at period start
  • Labor Hour Compliance
    • Actuals posted to work orders in the planning set / total work plan labor hours of the work orders in the planning set
  • Work Order Compliance
    • Number of completed work orders from the planning set / total work orders in the planning set
  • Break-in Work
    • Approved work orders inside the compliance period at period end, that were not in the planning set.
  • Break-out Work
    • Work orders from the planning set that are not in the compliance period at period end. Cancelled work orders are considered break-out work.
Schematic – data flow of one period
Advanced
  • Cron tasks for compliance start and end
    • SkdComplianceStartCronTask – schedules recurring period starts
    • SkdComplianceEndCronTask – Schedules recurring period ends
  • Allows Compliance to be calculated automatically, e.g. every week without user or admin intervention.
  • For example, if the planning meetings are from 6-7AM every Monday, resulting in a committed weekly schedule, the start cron might be set up to run Mondays at 8:00AM. If all completions and actuals are to be posted by 5:00PM every Friday, the end cron could run on Fridays at 6:00PM.
Best Practices
  • Save and commit a schedule after any edits and prior to starting or finishing a compliance period.
  • Double-check the schedule and actual hours posted before finishing the compliance period. A incorrect compliance period can be deleted, but since it already took place it cannot be regenerated.
  • Choose and stay with a consistent treatment of closed and cancelled records. By default, closed records count toward compliance the same way as completed; cancelled records count as break-out work.
  • Use snapshots or manual scenarios to save a picture or copy of the approved committed schedule at the start of a compliance period. This provides another useful reference of results after the fact.








#Scheduler
#Maximo
#MaximoScheduler
#AssetandFacilitiesManagement

Statistics
0 Favorited
55 Views
0 Files
0 Shares
0 Downloads

Comments

Mon June 03, 2024 08:25 PM

Hi Lori, 

Are there any more recent slides or demo or expanded explanations of scheduling compliance functionality. Specifically, around 7612 or 3 

I'd like to understand this in more detail than I find in the current help

TIA Geoff