Attaching a workload management policy

  • 1.  Attaching a workload management policy

    Posted Tue August 09, 2022 02:16 AM
    Hi Team,

    As we are attaching the workload management policy with the application, the instances are not working with the flow. As we are using instances foe MQ Flow, not seeing the threads connected with MQ Input.
    Please check the below images which we followed the steps for attaching the policy.
    Please let us know the steps that need to follow while using the workload management policy using policy project. 


    Thanks & Regards,
    Sneha Bobade


    ------------------------------
    Sneha Bobade
    ------------------------------


  • 2.  RE: Attaching a workload management policy
    Best Answer

    Posted Thu August 25, 2022 02:29 PM

    There is insufficient information here to assist.  You state that the instances are not working but you gave no evidence nor indicate what 'not working' means.  I noticed you have a rather large number of instances defined.  Most flows do not work well with a large number of instances.  You also do not have the option selected to start all instances with the flow.  This means instances will only be started as needed and deallocated when no longer needed.  ACE controls when that need is, not simply because you want them to be.

    Try enabling all the instances, but then closely monitor your CPU and performance as so many may have negative impacts.

    If that does not help, you need to explain what 'not working' means.

    MQInput also has a node level additional instance property (not all nodes have this).  If you use the node level property, it will not follow the policy config.



    ------------------------------
    MATTHEW SEGALL
    ------------------------------