    Posted Thu May 22, 2014 06:29 AM

    Hi All,

    I have some basic doubts regarding the 9.5 upgrade process,

    Is it possible to migrate the IS packages and process models from 8.0 to 9.5 directly or should i first migrate to 8.2 then followed by the migration from 8.2 to 9.5

    Thanks.
    Ganesh


    #Integration-Server-and-ESB
    #webMethods-Upgrade
    #webMethods
    #webMethods-General


  • 2.  RE: migrating process models from 8.0 to 9.5



  • 3.  RE: migrating process models from 8.0 to 9.5

    Posted Wed June 11, 2014 12:15 PM

    Hi Ganesh,

    For the IS packages, You can use Deployer to extract the packages from old to new envt. For BPM process, you can export the old process and import them in the latest Designer ad then publish it directly to the new version.

    For more detailed info, refer to chapter 10 of webMethods 95 upgrade guide.


    #webMethods
    #webMethods-Upgrade
    #Integration-Server-and-ESB
    #webMethods-General


  • 4.  RE: migrating process models from 8.0 to 9.5

    Posted Thu June 12, 2014 01:31 PM

    Hi,

    please note that Deployer usually does not allow deployment across versions, esp. when the first number is changing.

    Regards,
    Holger


    #Integration-Server-and-ESB
    #webMethods-General
    #webMethods-Upgrade
    #webMethods


  • 5.  RE: migrating process models from 8.0 to 9.5

    Posted Fri June 13, 2014 02:18 AM

    Hi Holger,

    Thanks for pointing out.

    You can in this case, export the Deployer build from older version and then import them in the newer version of Deployer.


    #Integration-Server-and-ESB