  • 1.  Force Start and End Activity Numbering

    Posted Wed June 29, 2022 11:58 AM

    We are looking to enforce Start and End numbering on our Blueprints. We can manually activate the "Include normal start and end events" option on the Numbering dialog per Blueprint which gives the desired results.

    Is there a way to set this option on as the default behaviour for anything created in Blueworks, or retrospectively enable it on multiple processes without updating them one by one?

    Thanks Simon



  • 2.  RE: Force Start and End Activity Numbering

    IBM TechXchange Speaker
    Posted Thu June 30, 2022 08:29 PM
    Hi Simon,

    At this time, this feature does not seem to be available in Blueworks Live, but it would be a great addition!

    We encourage to you to file a request for enhancement at https://dba.ideas.ibm.com/

    Thanks

    ------------------------------
    Stephanie Wilkerson
    IBM
    ------------------------------



  • 3.  RE: Force Start and End Activity Numbering

    Posted Fri July 01, 2022 06:38 PM
    Thanks - I have raised this!

    ------------------------------
    Simon Lant
    ------------------------------