  • 1.  Can link icons be combined?

    Posted Thu July 14, 2022 10:43 AM
    I have a series of activities that are executed multiple times in a process. I use links to connect to this series:


    Is there a method by which these multiple link icons can be consolidated into a single link icon?

    ------------------------------
    Tony Spielberg
    ------------------------------


  • 2.  RE: Can link icons be combined?

    Posted Fri July 15, 2022 05:16 PM
    Edited by Suzette Samoojh Fri July 15, 2022 05:16 PM
    Hi Tony,

    There isn't.  You could reduce the number of Link Events by merging lines via a gateway. That could reduce the number of Link Events, but you'd end up with an extra element in your diagram and it might not help you much if you have many long lines.



    It's an interesting use-case. I recommend logging an Idea here: https://dba.ideas.ibm.com/?project=BWL1

    ------------------------------
    Suzette Samoojh
    ------------------------------



  • 3.  RE: Can link icons be combined?

    Posted Mon August 01, 2022 10:33 AM
    Thanks!

    ------------------------------
    Tony Spielberg
    ------------------------------



  • 4.  RE: Can link icons be combined?

    IBM TechXchange Speaker
    Posted Wed July 20, 2022 04:24 AM
    Tony
    Have you considered creating a small process blueprint for the repeated steps and then using it as a linked process when required by your main process?

    ------------------------------
    Mark Ketteman
    Digital Business Solutions Engineer
    IBM United Kingdom Limited
    London
    ------------------------------



  • 5.  RE: Can link icons be combined?

    Posted Mon August 01, 2022 10:35 AM
    I have so considered. I chose not to do so because I wanted the details of the repeated process visible on the main diagram.

    ------------------------------
    Tony Spielberg
    ------------------------------