Hi
I recall AIX 7.1 TL5 SP3 being the minimum OS level/version which can run on POWER10(P8 compatibility mode)
my 2c...
-If you planning on migrating one of your own AIX LPAR's which doesn't have any Application's running etc...example a NIM environment then I would first perform a migration installation from AIX7.1 to AIX7.2/AIX7.3 on current POWER8; thereafter migrate the AIX LPAR to POWER10.
-If you are planning on migrating AIX LPAR's which are running Applications, I would approach the migration with a little more caution.
-Try to take the LPAR across to the P10 in its current state i.e AIX 7.1 (see minimum level above)
-Confirm with the Application Team that all is still working as it should now that you running on the POWER10.
-Plan to perform the migration installation from AIX7.1 to AIX7.2/AIX7.3 at a later stage to benefit from IBM Support,Security & Performance enhancements which comes with later versions of AIX.
Regards
------------------------------
Luke February
------------------------------
Original Message:
Sent: Thu May 30, 2024 05:01 AM
From: Arun kumar Rajendran
Subject: AIX 7.1 Migration to AIX 7.3
Planning to migrate from AIX 7.1 to AIX 7.3.
Currently POWER8 servers are holding AIX 7.1 LPARs. We are moving to POWER10 servers.
My understanding is we cannot upgrade AIX 7.1 to AIX 7.3 in POWER8 first and then move to POWER10 because it is not supporting.
Also AIX 7.1 we cannot move to POWER10 first and then upgrade to AIX 7.3 which is also not supporting
Our storage is in Nimble which contains AIX 7.1 LPARS filesystem
Kindly suggest a good method to upgrade and migrate it without any issue
------------------------------
Suthan
------------------------------