Scenario: 100 work orders - 50 of which are scheduled and approved in a given month. Three of them were approved, prior to the month's start, but are scheduled to be done on the first day of the month. NB: This is a non-rolling project.
Using a manual start/stopped compliance schedule, I started the compliance on the 4th day of the month, days 1 and 2 were the weekend and day 3 was a holiday, so not around to start on day 1. So, on day 4 at 11:03 AM I start off the compliance with a period of 1 month i.e. 1st of April t o 1st of May.
The number of Plan Work Records = 47, not 50!
The activities in the Graphical view show based on filtering that there are 50, so why are only 47 being monitored. NB: I can see that ones are being monitored using the SKDCOMPLIANCEWOLIST table.
Looking at the three not being monitored, it would appear that in fact they were completed at 10:25 AM on the 4th day, So, "just" before the compliance was started.
QUESTION 1Should the three records have been included? I ask because they are scheduled for the first day of the month.
QUESTION 2
Should the schedule have been refreshed before starting?
------------------------------
===============================