IBM Maximo Manage 9.x · Maximo Civil Infrastructure 9.3 · Spatial 9.3 · Linear assets · Hands-on guide
A highway, a railway track or a sewer main is one long asset. A work order that only says "I-95" is useless to a crew: they need to know which mile, which side, how far past which landmark. Maximo Civil Infrastructure adds the tools for that kind of asset to Maximo Manage: linear measures, features along the route, defects with a score and a position, work orders that cover a stretch and record how much of it is done, and possessions (the closure that keeps a crew safe while traffic is held back). This guide follows one stretch of interstate and one bridge on a live system, and explains every screen, field and number on the way.
Watch first: the whole lab in about six minutes, from milepoints to the lane closure, on the same records as the guide.
What you will learn
- What a linear asset is, how a linear referencing method turns "mile 23.4" into a position, and how specifications change mile by mile.
- How features (mile posts, guardrails, a bridge) are placed along the route and used as reference points.
- How an inspector raises a defect from a work order, classifies it, scores it and records exactly where it is.
- How a repair work order collects the defects it fixes and records progress stretch by stretch.
- How a possession work order (a lane closure) protects the work done inside it.
- How the road is drawn on a map from an ArcGIS layer, and how a stretch picked in the linear chart is shown on it.
- What a fresh install needs before the linear sections even appear, and how to switch them on safely.
Every step was run on a fresh Maximo Manage 9.3 system with the Civil Infrastructure, Spatial and HSE add-ons and the standard demo data. Record numbers in the screenshots are the ones the lab created.
BackgroundWhy linear assets need more than work orders
Most assets in Maximo sit in one place: a pump, a transformer, a lift. A road is different. Interstate 95 northbound through Maryland is 109.7 miles long. Its number of lanes, its speed limit, the county it crosses and the material under the wheels all change along the way. A guardrail runs from mile 20 to mile 25; a bridge carries it between mile 41.20 and 41.32. A crash bends the rail at mile 23.4 on the outside edge.
If the road is one asset with no measures, all of that ends up in free text, and nobody can answer simple questions: which defects are inside tonight's closure? How much of the resurfacing is finished? Is there already a repair planned for this stretch? If the road is cut into hundreds of small assets instead (one per tenth of a mile), every change in the road means re-cutting the assets, and history is lost each time.
Linear asset management solves this: the road stays one asset, and everything on it (specifications, features, defects, work) carries a start measure and an end measure along the road. Maximo Civil Infrastructure builds on the linear features of Maximo Manage and adds the civil engineering pieces: defects with a score and classification, bridge component structures, linear work progress and possessions.
TourThe Civil Infrastructure applications
The add-on installs its own versions of the main applications, all with "(Civil)" in the name. The ones used in this guide are in bold. It also uses two standard applications.
| Application |
What it is for |
| Assets (Civil) |
Linear and non-linear assets with features, linear specifications, defects (Work tab) and the linear chart. |
| Work Order Tracking (Civil) |
Work orders that cover a stretch: linear segment, Create Defect, linear progress, possession details and the Work in Blocked Area tab. |
| Locations (Civil) |
The same defect and linear tools for locations (for example a station or a yard). |
| Job Plans (Civil) |
Job plans with the possession fields, so a standard job can say it needs a closure. |
| Visual Inspection Models |
Links to Maximo Visual Inspection models that find defects in photos and drone images. |
| Features (standard) |
The catalogue of feature types: MP (mile post), GUARDRAIL, BRIDGE. |
| Security Groups (standard) |
Where the linear and possession options are granted (Step 0). |
ConceptsThe ideas, in plain words
All terms are also in the glossary.
- Linear asset: an asset that has a length and is described by positions along it: a road, a track, a pipe, a canal. In Maximo it has Linear? selected and a start and end measure.
- Measure: a distance along the asset from its start. On I-95N, measure 23.40 means 23.40 miles from the start of the road in Maryland (the Virginia line).
- Linear referencing method (LRM): the rule for reading measures: which unit, how offsets are measured, and where the zero is. I-95N uses MILEPOINT: measures in miles, offsets in feet. A railway track in the demo data uses FEET TO CM: typed in feet, stored in centimetres.
- Offset: a sideways (Y) or vertical (Z) distance from a reference line. The Y reference says which line: MIDLINE, CENTERLINE, EDGE-INSIDE, EDGE-OUTSIDE. The Z reference says which level: SURFACE, GROUND.
- Linear specification: a specification (attribute) that applies to a range of measures: 3 lanes from mile 0 to 25, 4 lanes from 25 to 50.
- Feature: something on or along the asset: a mile post (a point), a guardrail (a stretch), a bridge. A feature marked as a reference point can be used to locate other things ("0.3 miles past Bridge 1").
- Defect: damage found on an asset, recorded as its own record (class DEFECT) with a summary, a classification, a score from 0 (insignificant) to 5 (completely deteriorated) and, on a linear asset, a start and end measure.
- Defect classification: a tree that says what is damaged and how: for example DEFECT > SAFETY-BARRIER > RAILING > SAFETY-BARRIER BEAM. Civil ships a full bridge tree.
- Linear progress: rows on a work order that say which stretch is done, by whom and when.
- Possession: a period when part of the network is taken out of service and handed to the maintenance team: a lane closure on a road, a line blockage on a railway. In Maximo it is a work order of its own, and the work done inside it is listed on its Work in Blocked Area tab.
The big pictureHow the records connect
Figure 1. The four stages of the lab. Each box is a Maximo record or action; the numbers are the lab's records.
The labThe lab road and environment
The lab uses the Maryland highway data that ships with the Maximo demo database (site BEDFORD, organization EAGLENA):
| Record |
What it is |
| Asset I-95N |
Interstate 95 northbound, linear, LRM MILEPOINT, measures 0.00 (DC-VA line) to 109.70 (DE line). |
| Asset BR1 |
"Bridge 1", a bridge broken into 79 component assets following a bridge inspection standard. |
| Feature BRIDGE (new) |
A feature type added in Lab 2, then placed on I-95N at 41.20 to 41.32. |
| Work orders 1201, 1202, 1203 (new) |
Inspection, repair and possession, created in Labs 4, 6 and 8. |
| Defects 1180 to 1184 (new) |
Two guardrail defects on I-95N, three bridge defects on BR1 components. |
Software: Maximo Manage 9.3 with Civil Infrastructure 9.3 (database version V9300-06), Spatial 9.3 and HSE 9.3 (Civil needs both). The screenshots show the classic Manage applications. The map in Lab 9 uses an ArcGIS Online feature layer built from U.S. Census Bureau TIGER road data (public domain) and the Esri World Street Map basemap.
Step 0What a fresh install needs
Problem and benefitProblem: on a new system the Civil work order shows no linear segment, no progress table and no feature fields, so it looks like the product is incomplete. Benefit: one grant switches on the linear tools for the people who plan linear work, and nobody else.
Linear work management is opt-in. The fields and tables are tied to signature options (permissions inside an application), and a fresh install grants none of them to the administrators' group. In Security Groups, open your planners' group, go to Applications, select Work Order Tracking (Civil) and grant:
| Option |
What it shows |
| Linear Work Management |
Start and end measure, reference points and offsets on the work order. |
| Linear Progress Table |
The Progress table under each linear row (Lab 6). |
| Filter by Linear Assets |
A filter that finds work by asset and measure range. |
Users must sign out and in again; group rights are read at sign-in. On the lab system the grant was made with a small database configuration script that reads the administrators' group from the system settings and adds only the missing rows, so it can run again safely:
Text
INSERT INTO applicationauth (groupname, app, optionname, applicationauthid)
SELECT g.varvalue, s.app, s.optionname, NEXT VALUE FOR applicationauthseq
FROM (SELECT varvalue FROM maxvars WHERE varname = 'ADMINGROUP') g
CROSS JOIN (SELECT 'PLUSXWO' AS app, 'WMLINEAR' AS optionname
UNION ALL SELECT 'PLUSXWO', 'LINRPROG'
UNION ALL SELECT 'PLUSXWO', 'FLTRLASET' /* ... */) s
WHERE NOT EXISTS (SELECT 1 FROM applicationauth x
WHERE x.groupname = g.varvalue AND x.app = s.app
AND x.optionname = s.optionname)
Common mistake: granting the possession optionsThe possession section and the Work in Blocked Area tab are also options (PLUSXPOSDET, PLUSXPOSTAB). Civil already grants them to everyone with a condition (PLUSXPOSTABC: :plusxposswo = 1), so they appear only on possession work orders. Granting them again without the condition shows the tab on every work order. Check the Condition column in Security Groups before adding a grant.
Lab 1Read a linear asset
Problem and benefitProblem: road data lives in spreadsheets per county, and nobody is sure how many lanes a stretch has when planning a closure. Benefit: one asset carries every attribute by mile range, so any work at any measure can look up its road conditions.
- Open Assets (Civil), filter Asset on I-95N and open it.
- Scroll to Linear Referencing Details (Figure 2).
Figure 2. I-95N: (1) direction NORTH, (2) LRM MILEPOINT, (3) start measure 0.00 at the DC-VA line, (4) end measure 109.70 at the Delaware line.
The Direction matters: I-95 southbound is a separate asset (I-95S) with its own measures, because the two carriageways have different bridges, ramps and damage. The labels next to the measures (DC-VA Line, DE Line) say what is physically at the start and end.
- Open the Specifications tab (Figure 3).
Figure 3. Linear specifications: each row is (1) an attribute with (4) a value, valid between a start and an end measure (further right).
The demo data describes the road in 32 rows. A few of them, with their ranges:
| Attribute |
From |
To |
Value |
| LANES |
0.00 |
25.00 |
3 |
| LANES |
25.00 |
50.00 |
4 |
| SPEED |
0.00 |
55.00 |
65 MPH |
| SPEED |
55.00 |
56.00 |
45 MPH (Fort McHenry Tunnel) |
| COUNTY |
0.00 |
34.10 |
Prince George |
| AREA |
0.00 |
26.00 |
Suburban |
Work it outThe guardrail defect in Lab 4 is at measure 23.40. Read the table: 23.40 is below 25.00, so the road has 3 lanes there; below 55.00, so the limit is 65 MPH; below 34.10, so it is in Prince George county; below 26.00, so the area is suburban. A night closure of one lane leaves 2 of 3 lanes open, which is what the traffic plan in Lab 8 assumes.
Try it yourselfFind the number of lanes and the speed limit at measure 55.50. (Answer: 4 lanes, because 50.00 ≤ 55.50 < 75.00; and 45 MPH, inside the tunnel range 55.00 to 56.00.)
Lab 2Features along the road
Problem and benefitProblem: crews are sent to "mile 41.2" and have to count posts to find it. Benefit: features such as mile posts and bridges are placed on the asset, and work can be located relative to them.
Add a feature type
- Open Features and click New Feature.
- Feature: BRIDGE, description "Bridge carrying the roadway". Type: LINEAR (a bridge has a length).
- Save (Figure 4).
Figure 4. The BRIDGE feature type: (1) code and description, (2) type LINEAR, (3) not continuous, (4) reference point.
- Type: POINT for something with no length (a mile post, a sign), LINEAR for something with a start and an end (a guardrail, a bridge).
- Continuous?: selected when the feature must cover the whole asset with no gaps (for example pavement type). A bridge is not continuous.
- Is Reference Point?: Maximo selects it on new features. Keep it for landmarks crews can see, such as mile posts and bridges: they can then be picked in Start Feature Label and an offset typed from them.
Place the bridge on I-95N
- In Assets (Civil), open I-95N, tab Features, New Row.
- Feature: BRIDGE, Label: "BR1 Bridge 1", start Measure 41.20, end Measure 41.32. Save (Figure 5).
Figure 5. Features of I-95N: (1) feature type, (2) label, (3) start and (4) end measure. Mile posts are points (start = end); the guardrails and the bridge are stretches.
Work it outThe bridge is 41.32 − 41.20 = 0.12 miles long. One mile is 5,280 feet, so the bridge is 0.12 × 5,280 = 633.6 feet. The guardrail run from 20.00 to 25.00 is 5 miles, or 26,400 feet of rail.
Common mistakeUsing a POINT type for something with a length. A point feature has a single measure, so a bridge typed as a point has no length and cannot say where it ends. Choose the type before the first row is placed; check the From and To at the top of the Features tab for the measures the asset allows.
Lab 3A bridge as a structure of components
Problem and benefitProblem: a bridge inspection finds ten problems, and "Bridge 1 needs work" says nothing about which part. Benefit: the bridge is a tree of components, so each defect sits on the exact part (a bearing, an expansion joint) and its history follows that part.
The demo asset BR1 is broken down the way bridge inspection standards do it: wing walls, slopes, abutments, intermediate supports, bearings, the load-carrying superstructure (concrete and steel members), waterproofing, edge beams, safety barriers, surfacing and expansion joints. Open BR1, click the menu next to Asset and choose Open Drilldown (Figure 6).
Figure 6. The Drilldown shows BR1 and its first level of components. Each line opens further: Bearings > DB019 Bearings-C.
BR1 is a normal (non-linear) asset. It is tied to the road by the BRIDGE feature from Lab 2: the feature says where on I-95N the bridge is, the component tree says what the bridge is made of.
Lab 4Inspect a stretch and record defects
Problem and benefitProblem: inspectors write "rail damaged near exit 22" on paper, and the office types it later with the wrong mile. Benefit: the defect is created from the inspection work order with its exact measures, classification and score, and stays linked to the inspection that found it.
The inspection work order
- Open Work Order Tracking (Civil), New Work Order.
- Description "Guardrail inspection, MP 20 to MP 25", Asset I-95N, Work Type PM.
- In Linear Segment Details: start Measure 20.00, end Measure 25.00. Save: the lab got work order 1201 (Figure 7).
Figure 7. The inspection work order covers (1) a linear segment from (2) measure 20.00 to 25.00, exactly the guardrail run.
Instead of typing 20.00 you can pick Reference Point MP 20 and an offset of 0. Reference points are useful in the field: "MP 20 plus 3.4 miles" is something a crew can drive to.
Record a defect from the work order
- On work order 1201, click the menu next to Asset and choose Create Defect (Figure 8).
Figure 8. Create Defect sits in the Asset field's menu, not in the side menu.
- In the Create Defect dialog click New Row.
- Summary: "Guardrail post missing, rail sagging".
- Click the menu next to Select Defect Classification, choose Classify, and open the tree with the small arrows: DEFECT > SAFETY-BARRIER > RAILING > STANCHIONS > POSTS. Click the select icon on POSTS (Figure 9 shows the same tree for a beam).
Figure 9. The defect classification tree. The arrow opens a level; the icon before the name selects it. (1) is the safety-barrier beam used for defect 1180.
- Score: 4. The text next to the score explains the value (Figure 10).
- In Linear Segment Details: start Measure 24.10, end 24.12, Y Reference EDGE-OUTSIDE on both (Figure 11).
- Click OK, then save the work order.
Figure 10. The defect form: (1) classification path, (2) summary, (3) score. This one is defect 1180, created the same way from the asset.
Figure 11. Where the defect is: (1) an optional start feature label, (2) the measures in miles, (3) the Y reference: the outside edge, where the guardrail stands.
The score uses the RATING list:
| Score |
Meaning (as shown in Maximo) |
| 0 |
Insignificant. Little or no damage. |
| 1 |
Minor deterioration. Damage with a very slow rate of development. |
| 2 |
Early damage. |
| 3 |
Developed damage. Functional failure likely in a short time. |
| 4 |
Severely deteriorated. Functional failure very soon. |
| 5 |
Completely deteriorated. Component no longer functions. |
The lab created two guardrail defects this way:
| Defect |
Summary |
Classification |
Score |
From |
To |
| 1180 |
Guardrail beam bent after vehicle strike |
SAFETY-BARRIER BEAM |
3 |
23.40 |
23.46 |
| 1181 |
Guardrail post missing, rail sagging |
POSTS |
4 |
24.10 |
24.12 |
Work it outDefect 1180 is 23.46 − 23.40 = 0.06 miles = 0.06 × 5,280 = 316.8 feet of bent rail. Defect 1181 starts 24.10 − 20.00 = 4.10 miles past MP 20 (4.10 × 5,280 = 21,648 feet). The demo road has a mile post every 10 miles, so a crew would find it as "MP 20 plus 4.10 miles", or as 25.00 − 24.10 = 0.90 miles before the end of the guardrail run.
Because 1181 was created from work order 1201, Maximo filled Originating Record on the defect and linked the two in Related Records: the work order is the ORIGINATOR of the defect, and the defect is FOLLOWUP work of the work order. Anyone opening the defect later can see which inspection found it.
Common mistakeTyping the classification code into Select Defect Classification. The field holds a path in a tree, so a typed code is not accepted; use Classify and pick the node.
Common mistakeLeaving the linear segment at its default. A new defect on a linear asset starts with the whole asset (0.00 to 109.70). Saved like that, the defect says "somewhere on I-95" and shows up in every closure and every repair search.
Lab 5Defects on the asset and on the bridge
Problem and benefitProblem: an engineer planning a resurfacing does not know about the open damage reports on that stretch. Benefit: every defect on the asset is listed on the asset itself, with its score and measures.
Open I-95N in Assets (Civil), tab Work, sub-tab Defects (Figure 12).
Figure 12. Defects of I-95N with (1) score, (2) start and (3) end measure. (4) Refresh Defects reloads the list after changes in another application.
The Problem and Cause columns are empty for defects typed by hand. They are filled when a defect comes from photo-based detection (see Going further), which reads the category, type and cause from the image analysis.
For the bridge, defects are raised on the component assets with Create > Defect in Assets (Civil). Bridge components are not linear, so the dialog has no measures:
| Defect |
Component |
Summary |
Classification |
Score |
| 1182 |
DB023 Bridge slab |
Transverse cracks in slab soffit, span 2 |
CONCRETE STRUCTURE > CRACKS > Traffic impact |
2 |
| 1183 |
DB071 Joints |
Expansion joint seal torn, water reaching bearing shelf |
STEEL STRUCTURE > JOINTS > Wear |
4 |
| 1184 |
DB019 Bearings-C |
Bearing plate corroding under joint leak |
CONCRETE STRUCTURE > CORROSION > Flowing water |
3 |
Figure 13. The joint component DB071 with its defect 1183: (1) score 4, (2) status NEW.
Read the chainDefects 1183 and 1184 are one story: the torn joint seal (score 4) lets water run onto the bearing, which is now corroding (score 3). Fixing the bearing alone would not last; the joint has to be resealed first. Recording each defect on its own component, instead of one note on the bridge, is what makes that chain visible.
Lab 6The repair work order and its progress
Problem and benefitProblem: a repair is closed while half the rail is still bent, because the work order has only one status for 0.72 miles of work. Benefit: the repair lists the defects it fixes and records progress stretch by stretch.
Create the repair and link the defects
- In Work Order Tracking (Civil), new work order "Replace guardrail beam and post, MP 23.40 to 24.12", asset I-95N, work type CM (corrective maintenance), start measure 23.40, end 24.12. The lab got 1202.
- Tab Related Records, Select Tickets, filter Ticket on 1180 and 1181, select both, OK, save (Figure 14).
- Approve the work order and start it (status INPRG).
Figure 14. Work order 1202 with its (1) related defects of (2) class DEFECT, (3) relationship RELATED. The related work order at the top is the possession from Lab 8.
Work it outWhy 23.40 to 24.12? The repair must cover both defects: the first starts at 23.40, the second ends at 24.12. Length: 24.12 − 23.40 = 0.72 miles = 3,801.6 feet.
Record progress
- On the Work Order tab, in Multiple Assets, Locations and CIs, add a row for I-95N with start 23.40, end 24.12 and select Mark Progress?. Save.
- In the Progress table, New Row: Asset I-95N first, then start Measure 23.40 and end 23.80. Save (Figure 15).
Figure 15. One progress row: (1) the Progress table, (2) the stretch 23.40 to 23.80 miles, (3) who recorded it and (4) when.
Work it outDone: 23.80 − 23.40 = 0.40 miles. Planned: 0.72 miles. Progress = 0.40 ÷ 0.72 = 55.6 %. Left: 0.32 miles (1,689.6 feet), which includes defect 1181 at 24.10 to 24.12.
Common mistakeTyping the measures before the asset in a progress row. Without the asset Maximo cannot check the measures and clears them. Set Asset first.
Lab 7The linear chart
Problem and benefitProblem: a list of work orders does not show that three crews are working on the same mile next week. Benefit: the chart draws every work order and its progress against the miles of the road.
Open I-95N, tab Work, and scroll below the work order list (Figure 16).
Figure 16. The linear chart. The top scale is the measure in miles ("Zoom to tens" shows ten-mile steps). Each work order is a green bar over its stretch; the blue bars under Progress are the stretches recorded as done, with their dates.
Reading the demo rows: work order 1167 "Supervisor Monthly Driving Inspection" covers the whole road, and its progress shows the first 40 miles driven in four ten-mile stretches on four days. Work order 1170 "Annual Condition Assessment" was done in four stretches of about 25 miles. The Features and Relationships rows open the same way.
Try it yourselfScroll the chart down to work order 1202 and zoom in on miles 20 to 30. Compare the length of its progress bar with its green bar: the ratio is the 55.6 % from Lab 6.
Lab 8The possession (lane closure)
Problem and benefitProblem: the crew turns up for a night job and the lane closure was booked for a different stretch, or not at all. Benefit: the closure is a work order with its permit numbers, and the work allowed inside it is listed on it.
Create the possession
- New work order "Night lane closure (possession), MP 23.00 to 24.50", asset I-95N, start 23.00, end 24.50. Select Is Possession WO? and save. The lab got 1203.
- Reopen the work order: the Possession Details section and the Work in Blocked Area tab now appear (they are shown only when Is Possession WO? is selected).
- Possession Application Number: PA-2026-1107 (the request to the traffic authority), Possession Authorization Number: PAU-55821 (the approval), select Engineering Machines? (a crane truck will be inside).
- Scheduled Start 10/27/26 9:00 PM, Scheduled Finish 10/28/26 5:00 AM. Save (Figure 17).
Figure 17. Possession Details: (1) the work order is a possession, (2) application and (3) authorization numbers, (4) engineering machines inside the closure.
On a railway the same section also records a traction interruption (the overhead power is switched off) with its own application and authorization numbers, and interval blocking (trains are held between two signals).
Put the repair inside the closure
- Open repair work order 1202, select Requires Possession?, set Scheduled Start 10/27/26 10:00 PM and Scheduled Finish 10/28/26 3:00 AM. Save.
- Open possession 1203, tab Work in Blocked Area, Select Work Orders. On the lab system the dialog listed one candidate, 1202, the work order that requires a possession on this stretch; select it and click OK. Save (Figure 18).
Figure 18. The closure (1, 2) from 23.00 to 24.50 contains (3) repair 1202; (4) Select Work Orders adds more. The chart below draws the repair inside the closure.
Work it outSpace: the repair (23.40 to 24.12) must fit inside the closure (23.00 to 24.50). It does, with 23.40 − 23.00 = 0.40 miles of buffer before and 24.50 − 24.12 = 0.38 miles after, room for the taper of cones and the crane truck. Time: the closure is 9:00 PM to 5:00 AM = 8 hours; the repair is 10:00 PM to 3:00 AM = 5 hours, leaving 1 hour to set up the closure and 2 hours to clear it before morning traffic.
Common mistakeBooking the closure for the repair's exact stretch. Cones, signs and machines need room on both sides; a closure that ends at 24.12 leaves the crew at the very edge of live traffic.
Lab 9The road on a map
Problem and benefitProblem: "MP 23.40 to 24.12" means nothing to a dispatcher, a traffic officer or a contractor who does not know the road. Benefit: the same measures are drawn on a map, so anyone can see where the work is, which junctions are close and how far the crew must travel.
With Maximo Spatial, the Map tab of Assets (Civil) draws the road from a GIS layer. Because the road's line carries measures, Maximo can turn any start and end measure (a work order, a defect, a closure) into a piece of that line. Four things are needed: a GIS layer with the road, a map definition in Maximo that uses it, a link between the asset and its GIS feature, and the map tools switched on for the application.
The GIS layer
The lab road is a single polyline for I-95 northbound through Maryland, built from the U.S. Census Bureau's TIGER road data (public domain) and published to ArcGIS Online as a hosted feature layer, Civil_Lab_I95N, layer 0 "Linear assets". The line stores a measure at every vertex (an M value), from 0.00 at the Virginia line to 109.70 at the Delaware line, the same range as the asset. Its attributes hold ASSETNUM I-95N and SITEID BEDFORD.
Why M values matterA line without measures only has a length. With M values, "mile 23.40" is a defined point on the line even where the road was re-surveyed or the line has more vertices in towns than in the countryside.
The map definition (Map Manager)
- Open Map Manager and the demo map LBS_DEMO (Figure 19).
- Section Web Map Configuration: select Layers Configured with Web Map Definitions? and enter the Web Map ID of an ArcGIS web map that contains the road layer (Figure 20).
- Section Map Security: select Enable Token Security?, enter the ArcGIS user in Default Token User Name, click Set GIS Default Token Password and type the password (Figure 21). Maximo now asks ArcGIS for a token as that user, so the layer itself can stay private.
- In Map Services, click Select Map Services, pick the web map's service Civil_Lab_I95N and give it order 0 (drawn on top). The basemap, World Street Map, has order 100. Save.
- Open the new service row, Service Layers, Select Layers, pick layer 0 and run Execute GIS Configuration. Maximo creates a GIS object (here CIVLI95N) that reads the layer's features as if they were Maximo records, with ArcGIS as the System of Record (Figure 22).
- In GIS OBJECT Relationship Configuration, set the parent object to ASSET and the rule that joins a feature to its asset. The lab uses
OBJECTID=:PLUSXGISOID: the feature's ArcGIS id is kept on the asset.
Figure 19. Map Manager, map LBS_DEMO: (1) web map and (2) security settings, (3) the map services, drawn in order (0 on top), and (4) Select Map Services, which lists the services of the web map.
Figure 20. Web Map Configuration: (1) the layers come from a web map, (2) its ID in ArcGIS Online, (3) no OAuth application login, because this web map is shared publicly.
Figure 21. Map Security: (1) token security on and (2) the ArcGIS user Maximo signs in as. The password is set with the button on the right and is never shown.
Figure 22. The road layer inside Maximo: (1) Select Layers, (2) the GIS object CIVLI95N created for layer 0, and (3) ArcGIS as the system of record: the geometry lives in ArcGIS, Maximo keeps the link.
Common mistake: pasting the layer URLTyping the feature layer's own URL (.../FeatureServer) as a map service fails: Map Manager accepts feature layers only through a web map. Build a web map that contains the layer, enter its Web Map ID, then use Select Map Services.
Common mistake: private web map, no OAuthIf the web map itself is private, Maximo refuses the Web Map ID until Enable OAuth 2.0 Application Login Authentication?, a Client ID and a client secret are set. Either register an ArcGIS application for Maximo, or share the web map (not the layer) publicly and keep the layer behind token security, as the lab does.
Fresh install: three more gapsCertificates. The Maximo server must trust the certificates of the ArcGIS sites it calls (the services host, www.arcgis.com and the basemap host). On the lab system the server's trust store held none of the public certificate authorities, so every map call failed with a PKIX error until the ArcGIS certificate chains were imported and the server restarted. In MAS, add them to the Manage workspace's imported certificates.
Basemap. The demo map's default basemap is a vector tile service that needs an ArcGIS key. Replace it with a basemap that answers without one, such as World Street Map (https://services.arcgisonline.com/ArcGIS/rest/services/World_Street_Map/MapServer).
GIS object fields. The attribute list that Execute GIS Configuration offers for the new GIS object may not include the fields you need for the join (ASSETNUM, SITEID) or for the link. Add them to the GIS object as non-persistent attributes in Database Configuration, map them in the GIS object's JSON mapping, and add the persistent field that keeps the feature id on the asset (the lab's PLUSXGISOID). Without it, Link answers with BMXAA0019I and nothing is stored.
Link the asset to its feature
- Open I-95N in Assets (Civil), tab Map. The basemap and the road appear (Figure 23).
- Choose the Identify tool on the right-hand toolbar and click the blue line. The panel shows the feature's attributes (ASSETNUM I-95N, SITEID BEDFORD).
- Click Link. Maximo stores the feature's id on the asset (PLUSXGISOID) and marks the asset as linked to GIS. From now on the asset knows its own geometry.
Figure 23. The Map tab of I-95N: the road in blue from the Virginia line at the Wilson Bridge (measure 0.00) through Baltimore to the Delaware line (109.70). The tools on the right include Layers, Identify and the linear tool.
From the linear chart to the map
- Still on the Map tab, open the linear tool on the right-hand toolbar. The linear chart from Lab 7 docks under the map.
- Click the green bar of work order 1201 (the guardrail inspection, MP 20.00 to 25.00). Maximo converts the measures to the map's unit and draws that stretch in orange; the map centres on it (Figure 24).
- Click the bar of 1202 (MP 23.40 to 24.12): the highlight jumps to the 0.72-mile repair inside the inspected stretch.
Figure 24. Click a bar in the chart (bottom) and the map (top) draws its stretch in orange: work order 1201, MP 20.00 to 25.00, on the Capital Beltway through Greenbelt up to where I-95 leaves the Beltway near Beltsville. Measure 0.00 is the Wilson Bridge at Alexandria. Rows of other demo work orders are hidden in this figure.
Work it outThe server converts measures with the U.S. survey mile, 1,609.3472 m. Start: 23.40 × 1,609.3472 = 37,658.72 m. End: 24.12 × 1,609.3472 = 38,817.45 m. Length: 38,817.45 − 37,658.72 = 1,158.73 m, which is 0.72 miles. The map walks 37.66 km along the line from measure 0 and draws the next 1.16 km.
Known issue: the highlight on the new mapOn Manage 9.3 with the new map component (the one in Figure 23), the chart-to-map highlight does not work out of the box: the clicked stretch is drawn a few metres from the start of the road or not at all, closing the linear tool blanks the map until the record is reloaded, and an asset that is not linked to a GIS feature raises an error. The cause is in the shipped code (unit conversion, closing the tool, and the highlight style), not in the configuration. The lab system ran with temporary corrections to show the intended behaviour; on your system, report it to IBM support with these symptoms. The chart also opens as a strip under the full-height map: scroll the page to see it.
Going furtherPhoto-based defect detection
Photo-based detection. Work orders have Requires Photo Analysis in the Defect Detection Application? and a Defect Detection Folder. Photos or drone images taken along the stretch go into that folder; Maximo Visual Inspection models (managed in Visual Inspection Models) find cracks, spalling or corrosion in them, and the Defect Detection application creates defects from the findings, carrying the category, type and cause from the image analysis: the columns that stay empty for defects typed by hand.
SummaryCommon mistakes
| Mistake |
What happens |
Fix |
| Linear options not granted |
No linear segment or progress on the work order |
Grant Linear Work Management and Linear Progress Table (Step 0) |
| Possession options granted without condition |
Blocked-area tab on every work order |
Leave Civil's conditional grants in place |
| Defect left at the whole asset |
Defect matches every search on the road |
Set start and end measure |
| Classification typed |
Value not accepted |
Use Classify and pick the node |
| Progress measures before asset |
Measures cleared |
Set Asset first |
| Closure equals the repair stretch |
No room for cones and machines |
Add a buffer at both ends |
| Feature layer URL typed as a map service |
Service rejected |
Use a web map and Select Map Services (Lab 9) |
| ArcGIS certificates not trusted |
Map stays empty, PKIX errors |
Import the ArcGIS certificate chains |
| No field for the feature id on the asset |
Link stores nothing |
Add the field and use it in the relationship rule |
PracticeExercises
- Add a point feature SIGN and place an overhead sign on I-95N at 33.40 with Y reference EDGE-OUTSIDE. Which county is it in? (Prince George: 33.40 < 34.10.)
- Record the remaining progress on 1202 (23.80 to 24.12) and work out the new percentage. (0.72 ÷ 0.72 = 100 %.)
- Create an inspection work order for Bridge 1 and raise a defect on DB061 (safety-barrier beam) from it. Check that the defect shows the work order as originating record.
- A second repair needs MP 24.40 to 24.70. Can it go inside closure 1203? (No: 24.70 is past 24.50. Extend the closure, or book a second one.)
- On the map, click the bar of possession 1203 (MP 23.00 to 24.50). How long is the orange stretch in metres? (1.50 × 1,609.3472 = 2,414.0 m.)
- The speed limit at 55.50 is 45 MPH. Why would a closure there need a longer buffer than one at 23.40? (Tunnel: no shoulder, and traffic cannot be moved to the side.)
ReferenceGlossary
| Linear asset |
An asset described by positions along its length: a road, track, pipe or canal. |
| Measure |
Distance along a linear asset from its start, in the unit of its LRM. |
| LRM |
Linear referencing method: the unit and rules for measures and offsets (MILEPOINT, FEET TO CM, KILOMETERPOINT). |
| Milepoint |
A position in miles from the start of the road. |
| Y offset / Y reference |
Sideways distance from a line across the road (midline, centre line, inside or outside edge). |
| Z offset / Z reference |
Vertical distance from a level (surface, ground). |
| Linear specification |
An attribute value valid over a range of measures. |
| Feature |
Something on or along a linear asset; a point (mile post) or a stretch (guardrail, bridge). |
| Reference point |
A feature other positions can be measured from, with an offset. |
| Defect |
A record of damage (class DEFECT) with summary, classification, score and position. |
| Score / rating |
Condition of the damage from 0 (insignificant) to 5 (no longer functions). |
| Classification |
A node in a tree of defect kinds, such as SAFETY-BARRIER BEAM. |
| Originating record |
The record a defect or work order was created from. |
| Linear progress |
Rows recording which stretch of a work order is done, by whom and when. |
| Possession |
A closure of part of the network for maintenance (lane closure, line blockage), held as a work order. |
| Traction interruption |
On electrified railways: switching off the overhead power during a possession. |
| Interval blocking |
On railways: holding trains between two signals so a section is free. |
| M value |
A measure stored at each vertex of a GIS line, so positions along it can be found by measure. |
| Web map |
An ArcGIS item that lists layers and a basemap; Maximo reads its layers through the Web Map ID. |
| GIS object |
A Maximo object that reads features of a GIS layer, created by Execute GIS Configuration. |
| Token security |
Maximo signs in to ArcGIS as a named user and sends the token with each map request. |
| Signature option |
A permission inside an application, granted per security group, optionally with a condition. |
ReferenceLab records
| Record |
Key facts |
| I-95N |
MILEPOINT 0.00 to 109.70; features MP 10 to MP 100, GUARDRAIL 12 to 13 and 20 to 25, BRIDGE 41.20 to 41.32 |
| WO 1201 |
Guardrail inspection, MP 20.00 to 25.00, PM |
| WO 1202 |
Repair, MP 23.40 to 24.12, CM, INPRG; defects 1180, 1181; progress 23.40 to 23.80; requires possession |
| WO 1203 |
Possession, MP 23.00 to 24.50, PA-2026-1107 / PAU-55821, 21:00 to 05:00; contains 1202 |
| Defects 1180 to 1184 |
1180, 1181 on I-95N; 1182 slab DB023; 1183 joint DB071; 1184 bearing DB019 |
| Map LBS_DEMO |
Web map service Civil_Lab_I95N (order 0, GIS object CIVLI95N, rule OBJECTID=:PLUSXGISOID), World Street Map (order 100), token security on |